Estimating

This section is a lil’ incomplete. We have a lot of internal knowledge about how we estimate and break down projects, and this is a subset of that information.

Estimating is hard. Humans are fundamentally bad at it. Being good at estimating is one reason why our customers keep coming back to us.

  • We estimate using powers-of-two, e.g. 1, 2, 4, 8, 16.
  • However when we’re actually building something, we strive to ensure no tickets are larger than a four, taking time to work with the product owner to break down stories into smaller pieces of functionality. This is especially important if the project is running one-week sprints.
  • We’ve found Planning Poker works well for giving user stories accurate size estimates.
  • It should be done with as many of the development team as possible, ideally all of them, so everyone feels connected to the final estimates.
  • It takes a long time, but we’ve found it always pays off.
  • When we’re remote, we use our Planning Poker tool.
  • Once we’ve estimated story points using planning poker, we estimate our team’s starting velocity.
  • We use Velocitaire to do this quickly - it’s just an estimate!